Its amazing how long things take when you either stop to admire your work so far or you measure everything a 100 times. I am guilty of both and probably wasted an hour doing both today. Never mind. I did get the roof
I got in to the shed today and the paint had not fully cured. I toyed with the idea of giving it a second coat, but decided against it. I also decided against painting the underside of the top before gluing it on, it
I had a fairly easy day today, just preparing for a big day of rope wet out and inserting into the troughs later in the week when I have some help lifting the 7 meter rope. I will wet it out on the cutting bench on a
Because the next uni sets are 6 or 7 layers, and because I want to complete the wet out start to finish, I don’t get enough time on weeknights to finish so I cant start them. I will do them on the weekend. In the
Back on the real boat today and I managed in 5 hours what it took me 7 hours to do last Sunday. I coved, taped, and bogged the starboard hull to underwing join. Some of that extra 2 hours last week was preparation for
Today was a tough day. I thought I might get both hull to underwing joins coved and taped today but I worked all day (7 hours) and only managed to get one done. I did manage to bog the tapes though. It took me about 5
After a couple of days in Melbourne I got back to work on the boat. Today I taped the topside deck to chamfer joins. I filled the remaining gaps that were under the tabs as I went and then taped onto the wet filler. I
I have applied the last tape, so the starboard hull is now officially ready to turn. There is nothing more to do to this hull until it is turned. After I turn it, I still have the keel centre to tape on both hulls and
I have just over an hours work to do until I can say I have finished the starboard hull to the turnover stage. I have coved and taped all but 1 of the bulkhead to hull panel joins, with just the aft most bulkhead join
This past week I managed a couple of 3 hour stints in which I was able to tape 2 bulkheads each time. I coved and taped the 4 bulkhead sides inside 2 of the front 3 sealed buoyancy chambers (between BH1 & 2 and BH2